"How long will it take?" usually comes right after "What will it cost?" The honest answer is that the construction you can see is often the shorter part. Design, selections, pricing, permits and ordering come first, and the choices made in those months shape how smoothly the building goes.
This guide walks through each phase of a typical kitchen or bathroom remodel, what tends to cause delays, especially in older St. Louis homes, and how to keep a schedule on track. Treat the numbers here as benchmarks, not promises. Every project needs its own schedule.
- In Houzz's 2026 study, kitchens averaged 9.5 months of planning and 5.8 months of construction. Primary bathrooms averaged 8.4 and 4.8 months.
- Planning often takes longer than building. Finishing design and selections before demolition is the best schedule protection you have.
- Order long-lead items early. Custom cabinets alone can take six to eight weeks to build.
- In the City of St. Louis, most trade permits are approved in one to three business days, but plan review and historic district review can add time.
- Older homes hide surprises. Leave room in the schedule, and the budget, for what demolition reveals.
What the national numbers say
Houzz surveys its users every year. Its 2026 U.S. Houzz and Home Renovation Trends Study, covering projects done in 2025, reports that "kitchen projects have the longest timeline overall, with an average of 9.5 months spent on planning and 5.8 months spent on construction." Primary bathrooms averaged 8.4 months of planning and 4.8 months of work. Additions were excluded.
| Project (Houzz, 2025 projects) | Planning | Construction |
|---|---|---|
| Kitchen | 9.5 months | 5.8 months |
| Primary bathroom | 8.4 months | 4.8 months |
Keep two caveats in mind. These are averages reported by registered Houzz users in a survey fielded January to March 2026, not a random sample of every homeowner, and they are not broken out by project size. And schedules move in both directions: in the consumer survey behind the 2025 Remodeling Impact Report from the National Association of Realtors and NARI, 37 percent of homeowners said their project took about as long as planned, 31 percent said it took more time and 31 percent said less. About a quarter of those respondents did the whole job themselves.
The lesson is in the shape more than the totals. Houzz found that planning often takes longer than construction, and planning is the part you control most.
Before construction: design, selections and pricing
Consultation
The first meeting is where you and the contractor walk the space, talk through what is not working and settle on a rough scope and budget range. Bring photos, measurements, a budget range and a list of must-haves. Our consultation checklist covers what to prepare.
Design and drawings
Next comes the plan: measured existing conditions, layout options, drawings and, where structure changes, engineering. Expect a few rounds of revisions. Each round goes faster when one or two people in the household can make the final call.
Selections
Cabinets, counters, tile, fixtures, lighting, appliances, hardware and paint all need choosing, and many depend on each other: the sink depends on the counter, which depends on the cabinets. In Houzz's 2026 kitchen study, 91 percent of renovating homeowners upgraded countertops, 85 percent upgraded backsplashes and sinks, and 84 percent upgraded cabinets. That is a lot of decisions, and they are best made before demolition.
Pricing and contract
With design and selections settled, the scope can be priced in detail and written into a contract with a schedule. Read the schedule as carefully as the price. Ask what it assumes about your decisions, lead times and inspections, and how a change would affect it.
Permits and approvals in St. Louis
Who issues your permits depends on where you live. The City of St. Louis has its own Building Division. In St. Louis County, some municipalities run their own building departments and others rely on the County. Our St. Louis remodeling permits guide sorts out who handles what. Some benchmarks:
- City trade permits. For electrical and plumbing work, the City says to expect an approved permit or feedback within 10 business days, and most applications are approved within one to three. Plumbing permits go only to City-licensed plumbing contractors.
- City building permits. Which City staff and agencies review a building permit depends on the project, and complex projects may need several review meetings. The City's building permit page gives no standard turnaround, so ask for a current estimate.
- City historic districts. Applications for exterior work on City Landmarks and in City historic districts go to the Cultural Resources Office automatically. Compliant ones are usually approved within a few days. Work that does not meet the district's standards takes longer, and larger projects may go to the Preservation Board, which meets once a month.
- County municipalities. Ladue says permit review can take two to three weeks. Des Peres quotes seven to 10 business days with no expedited option. In Sunset Hills, the city's zoning approval normally takes about two weeks, and St. Louis County will not accept plans without it.
Order long-lead items before demolition
The fastest way to lose weeks is to tear out a kitchen and then order the cabinets. Long-lead items should be chosen, ordered and, ideally, confirmed before the room comes apart. Common ones:
- Cabinets. Angi notes that custom cabinets can take six to eight weeks to build, while stock cabinets can ship when ordered.
- Stone and quartz counters, which are usually measured after the base cabinets are installed and then fabricated, so they follow the cabinets by design.
- Special-order tile, plumbing fixtures, appliances and lighting.
- Windows and exterior doors, especially custom sizes for older openings.
Ask your contractor which items on your list carry the longest lead times and the date each one has to be ordered to hold the schedule.
Construction: demolition to final walkthrough
Demolition and discovery
Demolition goes fast. What it uncovers may not. In older St. Louis homes, opening walls and floors can reveal outdated wiring, damaged framing, old piping and earlier repairs that were never done right. Each discovery needs a decision, and some need revised drawings, a permit revision or an extra inspection.
In a home built before 1978, federal rules add steps up front. A firm paid to disturb painted surfaces must be lead-safe certified, must give you EPA's Renovate Right pamphlet no more than 60 days before work begins, and must post warning signs and contain the work area before starting. Our lead-safe renovation guide explains what to expect.

Rough-ins and inspections
With the room open, plumbers, electricians and HVAC installers run new lines, the stage called rough-in. Then the inspector comes. Under the model International Residential Code (2018 edition), rough inspections of plumbing, mechanical, gas and electrical work "shall be made prior to covering or concealment," and the framing inspection follows once those pass. In Des Peres, for example, the city's framing inspection happens only after St. Louis County approves its rough mechanical, electrical and plumbing inspections.
Inspections are requested by the permit holder, often with notice: Ladue asks for requests by 3 PM, 48 hours ahead. A failed inspection means a fix and a second visit, which the schedule has to absorb.
Finishes
After inspections pass, the visible work goes in, in order: insulation and drywall or plaster repair, then cabinets, counters, tile, trim, paint, fixtures and appliances. Each trade depends on the one before it, and some steps need time to cure or dry. This is where one missing part or one late decision can stall the whole job.

Punch list and final inspection
Near the end, you and the contractor walk the space and list every small item left: a scuffed wall, a sticky drawer, a missing outlet cover. The final inspection must pass too. Under the model code it comes "after the permitted work is complete and prior to occupancy." Expect a few days to close the list, longer if a part has to be reordered.

What causes delays
Most delays trace back to a short list:
- Changes after work starts. Moving a wall or adding a window mid-project can mean new drawings, a permit revision and new orders. In Houzz's 2026 study, homeowners who went over budget most often blamed higher-than-expected prices, but 32 percent said the project was more complex than expected, 31 percent had changed the scope or design and 22 percent hit unexpected construction issues. Changes like these usually cost time as well as money.
- Late selections. A tile or faucet chosen after demolition can leave the crew waiting.
- Discoveries in older homes, from rotted framing to wiring that has to be replaced before the walls close.
- Inspections, whether a failed one or a wait for an open slot.
- Lead times and damaged deliveries. A late cabinet order or a cracked counter slab stops the finish sequence.
- Approvals, such as historic district review or a municipal zoning letter, that were not started early enough.
How to keep a schedule on track
- Finish design and selections before demolition, and get them in writing.
- Order long-lead items early and confirm delivery dates.
- Agree up front on how changes work: who approves them, how they are priced and how they move the schedule.
- Set a standing weekly check-in with your project manager, and answer questions within a day.
- Hold a contingency in time as well as money, especially in an older home.
- Plan the site: where crews park, where materials go and which entrance they use. In the City, a dumpster that blocks any part of a street or sidewalk needs a Blocking Right of Way permit.
- Hold off on "while you're at it" additions once work is underway, unless you accept the time they add.
Living through a remodel
- Set up a temporary kitchen. A table with a microwave, a toaster oven or countertop cooker, the coffee maker and the old refrigerator covers most meals. Plan on paper plates and washing up in a laundry or bathroom sink.
- Protect the rest of the house. Ask how dust will be contained, which entrance the crew will use and how floors along the path will be covered.
- Expect noise and short shutoffs. Demolition is loud, and water or power may be off for stretches during rough-in, so ask for notice. Check your city's construction hours: Ladue, for example, allows construction noise from 7 AM to 6 PM on weekdays and 9 AM to 5 PM on Saturdays.
- Keep kids and pets out of the work area. In pre-1978 homes, lead-safe rules require signs warning occupants to stay outside the work area until cleaning verification is complete.
- Count your bathrooms. If the project takes out your only full bathroom, plan where you will shower, or stay elsewhere for that stretch.
A realistic schedule is built around your scope and your decisions. At Modern Design + Build, the first consultation is free, and our own project managers and foremen run the work. Bring your must-haves and any dates that matter, and book a consultation to talk through which decisions need to come first.
- 2026 U.S. Houzz and Home Renovation Trends Study, Houzz
- 2026 U.S. Houzz Kitchen Trends Study, Houzz
- 2025 Remodeling Impact Report, National Association of Realtors and NARI
- How Much Does a Kitchen Remodel Cost? (updated September 4, 2026), Angi
- Apply for an Electrical Permit, City of St. Louis
- Apply for a Plumbing Permit, City of St. Louis
- Apply for a Building Permit, City of St. Louis
- CRO Applications and Permits, City of St. Louis
- Cultural Resources Office, City of St. Louis
- City Historic Districts, City of St. Louis
- Building Department FAQs, City of Ladue
- Permit Requirements, Forms and Inspections, City of Des Peres
- Residential Construction, City of Des Peres
- Municipal Zoning Approval (Building Permits), City of Sunset Hills
- 2018 International Residential Code, Chapter 1, International Code Council
- Lead Renovation, Repair and Painting Program, U.S. EPA
- 40 CFR 745.84, Information distribution requirements, eCFR
- 40 CFR 745.85, Work practice standards, eCFR